As Vice President of Colwill Engineering Mechanical, Scot Newman oversees all sales and operational activities for our mechanical division. Mr. Newman has in-depth experience in the design and installation of central chilled water plants, variable refrigerant flow systems, industrial ventilation and all other HVAC systems.

Design/Build Project Experience

  • June 1983 – March 2014
    Vice President of JA Green Plumbing and Mechanical Inc., VP in charge of Mechanical Division

Design/Build Projects

  • Feld Entertainment Headquarters
    - 500,000 sq. ft.
    - 1,500-ton chiller plant with 42 AHU’s
    - Completed August 2013
  • VA Outpatient Clinic- Tampa
    - 110,000 sq ft.
    - (6) chilled water VAV AHU’s
    - (137) VAV boxes
    - 500-ton chiller plant
    - Completed December 2013
  • Parallon/ HCA call center
    - 90,000 sq. ft. call center
    - 320-ton variable refrigerant flow LG system with ERV
    - Completed March 2013
  • Progress Energy- Crystal River
    - 72,000 sq. ft. central control building to nuclear power plant
    - Completed March 2013
  • Raytheon Corporate
    - 210,000 sq. ft. engineering lab/office
    - 2,250-ton chiller plant
  • USMC Reserve Center
    - 250-ton Chiller plant
    - Complete gut/rebuild of barracks, gym and office
    - Completed 2008